Kirkland Lake Generating Station Design Details
View the conceptual process diagram.
Location Kirkland Lake, Ontario, Canada
Size Nominal rating 138 MWe
Fuel Natural gas and wood waste. The facility is the worlds first combined-cycle integrated-fuels project.
Date of First Operation August 1990.
Development, Conceptual Design, Detailed Design, Construction Management, Commissioning/Start-Up and Operation Northland Power Inc. and Cogeneration Associates Limited
Wood Boilers 3 60,000 lb./hr. Deltak with 10 tonnes/hr. KMW combustors
Steam Turbines 1 25 MW Metropolitan Vickers 1 20 MW Parsons Generator /General Electric Steam Turbine
Gas Turbines 3 22 MW General Electric, LM2500 PE 1 30 MW General Electric, LM2500+ DLE
Heat Recovery 3 60,000 lb./hr. Deltak
Condensers 2 Resorcon Wet Surface Cooled
Emission Control 3 Joy Scrubbers See case study.
|